Do You Need a Permit to Remodel a Kitchen in Florida?

Which Florida kitchen remodel jobs need a permit, from new circuits and moved sinks to wall removal, and how Melbourne and Brevard County handle them.

Last updated: Checked against official sources: 11 min readBy the Florida Renovation Guide editorial teamTopic: Kitchen & Bathroom Renovations

The short answer

  • Replacing cabinets, countertops, flooring and electric appliances in the same places usually doesn't need a building permit in Florida.
  • New circuits, moved plumbing, gas work, a new ducted range hood, a new window or door, and removing a load-bearing wall generally do. The $7,500 permit exemption never covers the electrical, plumbing, mechanical, gas or structural parts.
  • Brevard County permits kitchens only in unincorporated areas such as Viera, Suntree and Merritt Island; inside Melbourne, Palm Bay, West Melbourne or a beach town, the city or town issues the permit.
  • Unincorporated Brevard uses its Residential Renovation permit for remodels that add no square footage, with plans and an authorization for each subcontractor.
  • Electrical, plumbing and gas work needs licensed contractors (Brevard County has no handyman license) unless you do it yourself as a qualifying owner-builder.
On this page

You need a permit for a Florida kitchen remodel when the work goes past finishes: new electrical circuits, moved plumbing, gas lines, a new ducted range hood, a new window or door, or removing a load-bearing wall. Replacing cabinets, countertops, flooring and electric appliances in the same places usually doesn't need one. In Brevard County, which office issues the permit depends on your address: a city or town building department inside its limits, or the county for unincorporated areas such as Viera, Suntree and Merritt Island.

Kitchen work, line by line

Building departments look at what changes behind the cabinets, not at how much the kitchen costs. A high-end kitchen that keeps its layout can need fewer permits than a modest one that moves the sink.

Kitchen workPermit?Why
New cabinets and countertops in the same layoutUsually noHillsborough County, for example, lists cabinetry among work that typically doesn't need a permit
Backsplash tile, flooring and paintUsually noCosmetic finishes
Replacing electric appliances, a sink or a faucet in the same spot, on existing circuits and connectionsUsually noMoving any of them changes the answer
Swapping a gas range in the same spotAsk firstWe couldn't confirm how building departments treat a same-spot gas appliance swap, so ask yours before the installer disconnects the gas
Replacing a light fixture on an existing circuitUsually noLighting on a new circuit does need a permit
New circuits for an induction range, microwave, island outlets or under-cabinet lightingYesElectrical work, done by a licensed electrical contractor or a qualifying owner
Moving the sink or dishwasher, or adding an island sink or pot fillerYesNew drain and supply piping. In a slab home, the floor is cut for the drain.
Adding or changing a gas line, or moving a gas rangeYesGas work, which the $7,500 exemption never covers
A new ducted range hood through a wall or the roofGenerally yesExhaust ductwork, a wall or roof penetration and often a new circuit
Replacing or enlarging a window, or adding an exterior doorGenerally yesWindow and door permits check Florida product approval and the installation, and a bigger or new opening is structural work. See window and door permits.
Removing or changing a load-bearing wallYesStructural work, usually with an engineer's design
Removing a wall that carries no loadAsk firstSome departments treat it as minor work, but wiring, plumbing vents or ducts inside it need their own permits

Miami-Dade County's home renovation guidance makes the same point from the other side: new plumbing, electrical and mechanical work needs permits. The two places a "cosmetic" kitchen most often crosses the line are the island and the range. An island with a sink, a cooktop or outlets is plumbing and electrical work, and a new range can need a new circuit. Decide on both before you sign a contract, so the permit covers them from the start.

The $7,500 exemption rarely helps in a kitchen

Since July 1, 2026, Florida law lets single-family homeowners ask in writing to skip the building permit for some work valued under $7,500. It never covers electrical, plumbing, mechanical, gas or structural work, homes in a designated flood hazard area, or a bigger job split into pieces to get under the limit. In a kitchen, the work that needs a permit is almost always one of those excluded trades, and cabinet or countertop work that stays in place usually doesn't need a permit anyway. See the $7,500 permit exemption.

Who does what

A general, building or residential contractor can run the whole remodel but must subcontract plumbing, electrical and other licensed trades unless they hold those licenses, under section 489.113 of the Florida Statutes. Cabinet installers, tile setters, flooring installers and painters generally don't need a state contractor's license for that work alone, and since HB 735 (2021), local governments generally can't require a license for job scopes such as cabinetry, flooring, interior remodeling, tile and painting. Check their insurance and references, and make sure their work stops where the wiring, plumbing and gas lines start.

Doing the licensed work yourself is possible as an owner-builder, which makes you answerable for the work and its inspections the way a contractor would be. Florida also has a separate owner exemption for electrical work; see electrical permits in Florida.

Opening up the kitchen

Some interior walls in Florida homes carry roof loads, even in one-story homes, and some are concrete block. Removing a load-bearing wall requires a permit and usually an engineer's design for a beam or header. Even a wall that carries no load can hide circuits, plumbing vents and air conditioning ducts, each with its own licensed trade. Read removing a wall in Florida and how to tell if a wall is load-bearing before you plan an open layout.

Inspections and paperwork

Expect an inspection at each stage of permitted kitchen work: underground plumbing before a cut slab is patched, framing if a wall changed, rough electrical, plumbing and mechanical before the walls are closed, and a final. Don't let drywall, cabinets or backsplash tile go up over work that hasn't passed. See building inspections in Florida.

If the direct contract is over $5,000, Florida requires a recorded Notice of Commencement to be filed with the building department before the first inspection. Most permitted kitchen remodels cross that line; even the refresh tier in our Florida kitchen remodel cost guide starts above it.

In Melbourne and Brevard County

County or city: who issues your kitchen permit

Brevard County Planning and Development issues building permits only in the unincorporated parts of the county, such as Viera, Suntree and Merritt Island. Inside city or town limits, the city or town generally handles the permit; Melbourne, Palm Bay, West Melbourne, Rockledge, Titusville, Cocoa Beach, Indian Harbour Beach and Melbourne Beach are among those with their own permitting.

Postal names don't always match city limits, so a Melbourne mailing address doesn't tell you which office to use. Confirm with the county or your city hall before you apply. Our Brevard County permit guide lists each office and how it takes applications.

Unincorporated Brevard: the Residential Renovation permit

The county's permit type for a kitchen remodel is the Residential Renovation permit. It covers "minor repairs, renovations, or alterations (no additional square footage and not affecting the building footprint or new additional living space)," and the county gives an interior remodel as an example. A kitchen that grows into new square footage, such as a bump-out, falls outside that description, so ask whether it needs the county's Residential Addition permit instead.

What to expect (the county describes its permit pages as a general guide, and some projects need more documents):

  • Plans and subcontractor authorizations. The renovation page asks for plans and an authorization for each subcontractor. On a kitchen, that usually means the plumber and the electrician.
  • Separate trade permits. The county also has residential plumbing, electrical, HVAC/mechanical and demolition permit types. We couldn't confirm whether a kitchen's plumbing and electrical work goes on the renovation permit through subcontractor authorizations or needs its own trade permits, so ask the county with your scope in hand.
  • Windows and doors. The county permits exterior window and door replacements with a separate doors, windows and shutters permit, which asks for Florida product approval, the manufacturer's installation instructions and a floor plan showing each opening. If the remodel adds or enlarges a kitchen window or patio door, ask whether it goes on the renovation permit or its own.
  • Condos and other multi-family buildings. Remodeling a kitchen in a single unit goes through the county's separate Multi-Family Renovation permit.
  • How to apply. Licensed contractors file online in the county's BASS system, for work within their license type. Owner-builders file in person with the county's Owner Builder Application for Contractor Exemption; the Brevard County permit guide and our bathroom permit guide cover the rest of that process.

City of Melbourne

Inside Melbourne city limits, permits go through the Building Section of the city's Code Compliance Division, which takes applications in its EnerGov online portal. We didn't find a Melbourne page specific to kitchen remodels, so when you ask which permits apply, describe what moves, what's new and whether any wall changes. The city's fee schedule took effect August 7, 2026, and owner-builders should start with its owner-builder guide.

Melbourne also takes $7,500 exemption requests in EnerGov, for single-family homes outside a designated flood hazard area, and work shouldn't start until the Building Department approves the request in writing. Our Brevard County permit guide lists what the request needs. As explained above, few kitchens qualify.

Other Space Coast cities

  • Palm Bay asks for the contractor's state license or registration, general liability insurance and workers' compensation proof (or an exemption) with each application. Because the city can charge up to four times the permit fees for work started without a permit, don't let demolition get ahead of it.
  • Rockledge asks for a written, detailed narrative of the scope of work with each residential permit application, and a Notice of Commencement recorded with the Brevard County Clerk of Courts for projects of $5,000 or more.
  • Indian Harbour Beach has separate electrical, plumbing and HVAC permit checklists, so read the ones that match your kitchen's trades. Owner-builders apply in person with an affidavit and proof of ownership.
  • Melbourne Beach. The town's permit application says contractor licensing and insurance information must be current with Brevard County.
  • West Melbourne, Titusville and Cocoa Beach run their own building departments. We didn't find kitchen-specific rules for them, so ask. Satellite Beach's Community Development Department handles permits; ask it about the process. In Indialantic and the smaller towns, ask city or town hall who reviews permits.

Need a contractor for this project?Request a kitchen remodel estimate

Flood zones on the barrier island and along the lagoon

In a FEMA flood zone, a large kitchen remodel can trigger the substantial improvement rule. If the cost of the work equals or exceeds 50% of the building's market value before construction starts, the whole home generally has to meet current flood rules. For market value, Brevard County's flood-zone guidance allows an estimate based on the building's tax-assessed value (land and accessory structures excluded) plus about 15–20%, and an owner who disputes the figure can hire a state-licensed appraiser. For a substantially improved building, the county's guidance calls for an elevation certificate prepared by a licensed surveyor.

If you live on the barrier island, in Satellite Beach, Indian Harbour Beach, Indialantic or Melbourne Beach, or near the Indian River Lagoon, check your flood zone before you design. Count everything in the same project, not just the kitchen. The county's Floodplain Administration page has a flood zone map. Inside a city, ask the city's building department how it applies the rule. See the FEMA 50% rule.

Beachfront homes seaward of the state's coastal construction control line can face one more review: the Florida Department of Environmental Protection requires its approval for alteration or construction there, with certain exceptions. Ask DEP whether your kitchen work falls under one. See CCCL permits.

HOAs and condos

In a planned community, the HOA may need to approve exterior changes, such as a range hood vent through an outside wall or a new window. Since July 1, 2026, an HOA can't require a building permit before it reviews your application, so you can apply to both at the same time. Condo associations usually have their own rules on plumbing, contractors and working hours. See HOA approval in Florida.

Checking licenses in Brevard

A kitchen job often has a remodeler or general contractor, a cabinet installer, a plumber and an electrician on it. Brevard County has no handyman license, and it says electrical, mechanical and plumbing work, including remodeling and repairs, must be done by a licensed contractor. Local trade licensing has been changing since HB 735, so if you're unsure whether a particular installer's work is regulated, ask the county's contractor licensing office.

Look up each licensed company on MyFloridaLicense.com and on the county's Licensed Contractor Search, linked from its licensed trades page. Our guide to hiring a contractor in Melbourne explains what that search confirms and covers contracts, deposits and references.

Common mistakes

  • Letting the scope grow past the permit. Deciding mid-job to move the sink, add island outlets or take out a wall adds permit work. Raise it with your contractor before the work happens so the permit and inspections cover it.
  • Closing walls too soon. Rough plumbing and electrical have to pass inspection before drywall, cabinets and backsplash go in.
  • Counting on the $7,500 exemption. It excludes the trades a kitchen usually needs, and it takes a written request.
  • Hiring a handyman for wiring or plumbing. In Brevard, a handyman can do only unregulated work.
  • Applying to the wrong office. Confirm whether the county or a city has jurisdiction before you or your contractor apply.
  • Pulling an owner-builder permit for a contractor's work. If the contractor will do the work, the contractor should pull the permit.
  • Skipping the flood check on a big remodel. On the barrier island or near the lagoon, a kitchen plus other work can reach the 50% rule.
  • Paying in full before the final inspection. Keep the last payment until the permit is closed.

Next steps

  1. List what's changing: anything that moves (sink, range, dishwasher, walls) and anything new (circuits, a gas line, a vented hood, a window or door).
  2. Confirm whether your home is in unincorporated Brevard or inside a city or town, and look up that office's permit pages.
  3. For a large project on the barrier island or near the lagoon, check your flood zone and compare the project cost with the building's value.
  4. Get HOA or condo approval if your community requires it.
  5. Hire a licensed contractor and get in writing who pulls which permits. Record the Notice of Commencement if the contract is over $5,000.
  6. Keep the permit and final inspection records with your home documents.

For budgets, see kitchen remodel costs in Brevard County, the Florida kitchen remodel cost guide and kitchen cabinet replacement costs in Melbourne. If the bathroom is next, read bathroom remodel permits.

Frequently asked questions

Do I need a permit to replace kitchen cabinets?

Generally not, if you're not changing plumbing, electrical or walls. Hillsborough County, for example, lists cabinetry among work that typically doesn't need a permit. If the same job moves the sink or adds circuits, that part needs a permit.

Do I need a permit to move my sink?

Yes. Moving a sink means new drain and supply piping, which is plumbing work that needs a permit. In a slab home it also means cutting the floor for the drain, and the underground plumbing is inspected before the slab is patched.

Do I need a permit for a new range hood?

Replacing a recirculating hood on an existing circuit usually doesn't. A new ducted hood that goes through a wall or the roof, or needs a new circuit, generally does. An exterior vent may also need HOA approval.

Who issues kitchen remodel permits in Melbourne, Florida?

It depends on whether the home is inside city limits. Melbourne's Building Section handles kitchens inside the city, through its EnerGov portal. Brevard County Planning and Development handles unincorporated areas such as Viera, Suntree and Merritt Island, and Palm Bay, West Melbourne, Indian Harbour Beach, Melbourne Beach and other cities have their own building departments. Because a Melbourne mailing address can fall in either, check with the county or city hall before applying.

Which permit does Brevard County use for a kitchen remodel?

For a kitchen that stays within the home's existing footprint in unincorporated Brevard, the county uses its Residential Renovation permit, with plans and an authorization for each subcontractor. A bump-out that adds square footage may need the Residential Addition permit instead, and a condo kitchen goes through the Multi-Family Renovation permit. The county also has separate plumbing, electrical and mechanical permit types, so ask which ones your scope needs.

Does the $7,500 permit exemption cover a kitchen remodel?

Rarely. The exemption excludes electrical, plumbing, mechanical, gas and structural work at any price, and homes in a flood hazard area, and those trades are usually the parts of a kitchen that need a permit. It also takes a written request, and Melbourne says not to start until the city approves it in writing.

Official sources

We summarize official information in our own words and link to the source. Requirements can change, so confirm details with the source before relying on them. Our editorial standards

Project Costs

Kitchen remodel cost in Brevard County

What a kitchen remodel costs in Brevard County, from a refresh to a new layout, with local figures, sample budgets, permits and hurricane-season timing.

Permits & Regulations

Renovation permits in Brevard County

Which renovations need a permit in Brevard County, whether the county or your city issues it, and what Melbourne, Palm Bay and the beach towns require.

Permits & Regulations

Do I need a permit to remove a wall?

When removing or opening an interior wall needs a permit in Florida, how load-bearing and concrete block walls differ, engineering, inspections and costs.

Permits & Regulations

Electrical permits in Florida

When home electrical work needs a permit in Florida, certified vs. registered electricians, the owner exemption, generators, and how to check a license.

Permits & Regulations

Do I need a permit for a bathroom remodel?

Which Florida bathroom remodel jobs need a permit, from tub-to-shower conversions to new circuits, and who issues them in Melbourne and Brevard County.

Project Costs

How much does a kitchen remodel cost?

What a kitchen remodel costs in Florida, from a refresh to a full custom kitchen, with cabinet and countertop prices and what pushes budgets up.