Notice of Commencement in Florida: What It Is and When You Need One

What a Florida Notice of Commencement is, when it's required, how to record it, and how it protects you from paying twice under the construction lien law.

Last updated: Checked against official sources: 2 min readBy the Florida Renovation Guide editorial teamTopic: Permits & Contractor Guides

The short answer

  • A Notice of Commencement is a short form, signed by the owner and recorded with the county clerk, that officially starts a construction project under Florida's lien law.
  • The building department needs a recorded copy before the first inspection when the direct contract is over $5,000. Air conditioning repair or replacement is exempt under $15,000.
  • It names the owner, contractor, lender and anyone you designate to receive notices, so subcontractors and suppliers know who to notify.
  • Skipping it can leave you paying twice for the same work if your contractor doesn't pay subcontractors or suppliers.
On this page

If you hire a contractor for a sizable Florida project, you'll be asked to sign a Notice of Commencement. It looks like paperwork, but it's one of the main ways Florida's construction lien law protects homeowners, and skipping it can be expensive.

What a Notice of Commencement does

Florida's construction lien law lets subcontractors, laborers and suppliers who weren't paid file a lien against the property they improved, even if you paid your contractor in full. The Notice of Commencement is the public record that a project has started. It lists:

  • the property's legal description
  • a description of the work
  • the owner, contractor and any surety bond
  • the lender, if the project is financed
  • anyone the owner designates to receive copies of notices
  • the expiration date of the notice

Subcontractors and suppliers use it to send you a "Notice to Owner", which tells you they're working on your project and expect to be paid. That's how you know whose lien releases to collect before you pay. Our guide to Florida's construction lien law explains the whole process.

When is it required?

Florida requires the permit applicant to file a certified copy of the recorded Notice of Commencement, or a notarized statement that it's been filed for recording, with the building department before the first inspection when the direct contract is greater than $5,000. That threshold was raised from $2,500 in 2023. Repairing or replacing an existing heating or air conditioning system is exempt when the contract is under $15,000.

Some older county forms still show the earlier thresholds, so go by the current statute and your building department's instructions. Our guide to hiring a contractor in Melbourne covers how this works in Brevard County.

Need a contractor for this project?Find a Contractor

How to record one

  1. Get the form from your contractor, the building department or the county clerk's website.
  2. Fill in the details. The legal description comes from your deed or the property appraiser's record.
  3. Sign it in front of a notary. The owner must sign; a contractor can't sign on your behalf.
  4. Record it with the county clerk of court and pay the recording fee.
  5. Post a certified copy at the job site and give one to the building department before the first inspection.

Miami-Dade's guidance says the notice must be recorded within 90 days before work starts, and that it's generally good for one year unless a different date is stated. If your project runs long, ask how to extend it.

Protecting yourself after it's recorded

  • Keep every Notice to Owner you receive. Each one is a party you'll need a release from.
  • Before each payment, ask your contractor for lien releases from the subcontractors and suppliers who have sent notices, covering the work being paid for.
  • Before final payment, get the contractor's final payment affidavit listing anyone still unpaid.
  • Don't pay far ahead of the work. See contractor deposits in Florida.

Owner-builders

If you pull your own permit as an owner-builder, you're responsible for the Notice of Commencement and for paying everyone you hire. For contracts and payment terms, use our renovation contract checklist.

Frequently asked questions

Who records the Notice of Commencement, the owner or the contractor?

The owner must sign it in front of a notary, but contractors often prepare it and take it to the clerk. Either way, make sure it's recorded with the county clerk before work starts and that you keep a copy.

How long is a Notice of Commencement good for?

Generally one year from recording unless the notice states a different expiration date. Long projects may need a later expiration or a new notice. Ask your contractor or attorney.

How much does it cost to record?

County clerks charge recording fees by the page. One clerk lists $10 for the first page. Check your county clerk's fee schedule.

What is the warning on my permit card about paying twice?

Florida requires building departments to warn owners that failing to record a Notice of Commencement may result in paying twice for improvements. It's a reminder that the notice and lien releases protect you.

Need a contractor for this project?Find a Contractor

Official sources

We summarize official information in our own words and link to the source. Requirements can change, so confirm details with the source before relying on them. Our editorial standards

Renovation Guides

How Florida's lien law affects you

How Florida construction lien law works for homeowners: Notices to Owner, lien releases, the final affidavit and how to avoid paying twice.

Permits & Regulations

Building permits in Florida explained

How building permits work in Florida, who issues them, which projects need one, the new $7,500 exemption, permit timelines, inspections and closing out.

Renovation Guides

What a renovation contract should include

What a Florida renovation contract should include: lien and Recovery Fund notices, inspection-based payments, change orders, permits and storm delays.

Renovation Guides

How much should you pay up front?

How contractor deposits work in Florida: the 10% rule in section 489.126, special-order items, progress payments, lien releases and work that never starts.

Renovation Guides

Hiring a contractor in Melbourne, FL

How to hire a renovation contractor in Melbourne and Brevard: state and county license checks, Palm Bay registration, permits, deposits and storm scams.