Building Inspections in Florida: What to Expect and How Private Providers Work

How permit inspections work during a Florida remodel, common inspection stages, failed inspections, closing out a permit and using a private provider.

Last updated: Checked against official sources: 2 min readBy the Florida Renovation Guide editorial teamTopic: Permits & Contractor Guides

The short answer

  • Every permitted project gets inspected at set stages, and work shouldn't be covered until it passes.
  • Florida lets owners, or contractors with the owner's permission, hire a licensed private provider for plan review and inspections instead of the building department.
  • Local governments must reduce permit fees when a private provider is used. HB 803 (2026) set minimum reductions, mainly for commercial projects, so ask how fees are reduced for a home project.
  • Your permit isn't finished until the final inspection passes and the permit is closed.
On this page

Inspections are where the permit pays off for you as a homeowner: an independent inspector checks work you probably can't evaluate yourself, at the moments when problems are still visible.

Common inspection stages

The exact list depends on the project, but Florida remodels typically see some of these:

  • Footings or foundation, before concrete is poured (additions, decks, enclosures)
  • Underground plumbing, before a slab is patched
  • Framing and structural, including hurricane straps and connections, before drywall
  • Rough electrical, plumbing and mechanical, before walls are closed
  • Roof sheathing and dry-in, before the roof covering goes on
  • Windows and doors, checking the installation matches the product approval
  • Insulation, where required
  • Final, when the work is complete

Your permit card lists the inspections. Keep it posted where inspectors can see it, and don't let anything be covered until it has passed.

Need a contractor for this project?Find a Contractor

Failed inspections

A failed inspection isn't unusual, and it's much better than a hidden defect. The inspector lists what needs to be corrected, the contractor fixes it, and a re-inspection is scheduled. Tie your progress payments to passed inspections where possible; see renovation contract checklist.

Private providers

Florida's private provider law (section 553.791) lets you use a licensed private provider, such as a licensed building code administrator, inspector or engineer, for plan review and inspections instead of the building department's staff:

  • The owner, or the contractor with the owner's written authorization, chooses the private provider.
  • The building official must be notified in writing when you apply for the permit, or by 2 p.m. two business days before the first scheduled inspection.
  • The local government must reduce the permit fee to reflect the services it no longer provides. Reductions vary; the City of Miami, for example, has published reductions of up to one-third of the building department portion for plan review and inspections. HB 803 (2026) set minimum fee reductions, mainly for commercial projects, so ask your building department how fees are reduced for a home project.

Private providers can speed things up on larger projects, especially when building departments are busy after storms. They cost money, so compare their fee with the permit fee reduction and the time saved.

Closing out your permit

When the final inspection passes, the permit should show as finaled or closed in the building department's records. Check the online status, save a copy, and keep it with your Notice of Commencement and lien releases. Open permits regularly come up when you sell, and they can complicate insurance claims.

For timing, see how long renovations take in Florida. For permit basics, read building permits in Florida.

Frequently asked questions

Do I need to be home for the inspection?

Usually someone needs to provide access, which is often the contractor. Ask your contractor how inspections are scheduled and whether you'll be notified of results.

What happens if an inspection fails?

The inspector notes what needs to be fixed. The contractor corrects it and schedules a re-inspection, which may carry a fee. Don't pay for that stage of work until it passes.

Can I use a private inspector instead of the county?

Yes. Florida's private provider law lets the owner, or the contractor with the owner's authorization, hire a licensed private provider for plan review and inspections. You must notify the building official in writing when you apply for the permit, or by 2 p.m. two business days before the first scheduled inspection.

How do I check whether my permit was closed?

Most building departments have an online permit search showing inspection results and permit status. Look for a finaled or closed status, and save a copy.

Need a contractor for this project?Find a Contractor

Official sources

We summarize official information in our own words and link to the source. Requirements can change, so confirm details with the source before relying on them. Our editorial standards

Permits & Regulations

Building permits in Florida explained

How building permits work in Florida, who issues them, which projects need one, the new $7,500 exemption, permit timelines, inspections and closing out.

Permits & Regulations

Roof permits and the 25% rule

When a Florida roof replacement or repair needs a permit, how the 25% rule and the 2022 change work, reroof code upgrades, inspections and county differences.

Permits & Regulations

Do I need a permit to remove a wall?

When removing or opening an interior wall needs a permit in Florida, how load-bearing and concrete block walls differ, engineering, inspections and costs.

Permits & Regulations

What is a Notice of Commencement?

What a Florida Notice of Commencement is, when it's required, how to record it, and how it protects you from paying twice under the construction lien law.

Renovation Guides

How long do renovations take?

Realistic timelines for Florida remodels, from roofs and impact windows to kitchens and additions, with permits, HOA review and hurricane season.