Building Permits in Vero Beach and Indian River County

Who issues permits in Vero Beach, Sebastian, Fellsmere and the rest of Indian River County, the online portals and what work needs a permit.

Last updated: Checked against official sources: 6 min readBy the Florida Renovation Guide editorial teamTopic: Permits & Contractor Guides

The short answer

  • Indian River County's Building Division issues permits for unincorporated areas and for the City of Vero Beach, which shares the county's building department.
  • Sebastian, Fellsmere, Indian River Shores and Orchid run their own building departments, so check which one covers your address before you apply.
  • The county takes applications, payments and inspection requests through the MyGovernmentOnline (MGO) portal. Sebastian also uses MGO Connect.
  • Fences in unincorporated areas and Vero Beach need a permit with a survey or site plan, and reroofs follow the county's roofing inspection process.
  • State-certified contractors must register with the county before working in unincorporated areas or Vero Beach. Check every license at MyFloridaLicense.com.
On this page

Indian River County's Building Division issues building permits for the unincorporated county and for the City of Vero Beach. Sebastian, Fellsmere, Indian River Shores and Orchid each run their own building department. Start by finding out which one covers your address, because forms, portals and some local rules differ.

Who issues your permit

Where the property isWho issues building permitsHow to apply
Unincorporated county, including Vero Lake Estates, Gifford, Wabasso and unincorporated parts of the barrier islandIndian River County Building DivisionMyGovernmentOnline (MGO) portal
City of Vero BeachIndian River County Building Division (shared with the city)MGO, plus city planning approvals first
City of SebastianSebastian Building DepartmentMGO Connect customer portal
City of FellsmereFellsmere Building DivisionForms submitted to the city; see its page
Town of Indian River ShoresIndian River Shores Building DepartmentMoving to MGO; check the town's page
Town of OrchidOrchid Building DepartmentThrough the town; see its page

A Vero Beach or Sebastian mailing address doesn't tell you which jurisdiction you're in. If you're not sure, ask the county Building Division before you apply.

Vero Beach is a shared arrangement

The City of Vero Beach says it shares its building department with the county and sends permit questions to the county's website. The city still controls land use. Site plan approval, a historic preservation certificate of appropriateness or a code compliance approval from the city's Planning and Development Department is needed before a building permit is issued, and the county's checklist tells applicants for structures in Vero Beach to complete a separate city planning application.

Applying online through MGO

The county moved its permitting to MyGovernmentOnline (MGO) on July 10, 2023. Applications, fee payments, inspection requests, document uploads, inspection reports and approved plans all run through the portal. Homeowners and contractors create their own accounts.

For most remodeling work, the county uses a scope-of-work application. Its checklist asks for:

  • a detailed scope of work as a separate document
  • documentation of the job value, such as a signed contract or estimate
  • the owner-builder disclosure statement, if you're pulling the permit yourself
  • product approvals and other documents for the specific trade

The county says its review clock doesn't start until the application is complete, so a missing document delays everything. Sebastian's portal works the same way for most permit types; you apply, upload documents, pay and schedule inspections there.

What needs a permit

Rules below are for the county Building Division (unincorporated areas and Vero Beach) unless a city is named. For anything not covered, check your building department's forms page or call before work starts.

Reroofing

A roof replacement needs a permit. The county's roofing inspection guide says the approved permit documents and the Florida product approval or Miami-Dade Notice of Acceptance must be on site for inspection. It lets a roofing contractor file a roof sheathing affidavit instead of a sheathing inspection on reroofs, but owner-builders can't use the affidavit and need the inspection. That guide sits in the county's previous-code-year folder, so ask whether a newer version applies. Fellsmere and Indian River Shores publish their own reroof affidavit forms. For the 25% rule and reroof code upgrades, see our roof permit guide.

Windows, doors and garage doors

The county has its own permit application for garage doors, and replacement windows and exterior doors need product approvals for the wind loads at your site. Confirm with your building department what a size-for-size replacement needs. Our window and door permit guide explains product approvals and impact protection.

Screen enclosures

Confirm with your building department what a new or rebuilt enclosure needs; expect engineered drawings for the aluminum frame. Indian River Shores' 2026 post-storm permitting plan lists enclosure repairs and rebuilds as needing a permit and screen-only replacement in an existing enclosure as not needing one. See screen enclosure permits.

Fences

In unincorporated areas and Vero Beach, a fence needs a permit. The county's fence application asks for proof of job value and a survey or site plan showing the fence, its type, height, section lengths and gates. A fence serving as a pool barrier must be noted, and residential fence permits need planning sign-off. Indian River Shores has its own fence and wall checklist. See fence permits in Florida.

Sheds

Check with your building department before you buy or build a shed. Ask about setbacks, wind anchoring and whether a prefabricated shed needs a state approval. Our shed permit guide covers the common questions.

Small jobs under $7,500

Following the 2026 state law, the county offers a building permit exemption application for limited work under $7,500 on a single-family home. It doesn't cover electrical, plumbing, mechanical, gas or structural work, or property in a flood hazard area, and it isn't automatic. See the $7,500 permit exemption.

Need a contractor for this project?Find a Contractor

Owner-builder permits

The county accepts owner-builder applications with the disclosure statement required by section 489.103(7) of the Florida Statutes. The home must be for your own use or occupancy, not for sale or lease; you must supervise the work yourself and can't hire unlicensed people to act as your contractor. The county's licensing page notes that the owner exemption from contractor licensing doesn't waive the permit or its fees. Sebastian says owner-builder applications must start in person at its building department. Read our owner-builder guide before you choose this route.

Notice of Commencement

Florida requires a recorded Notice of Commencement before the first inspection when the direct contract is over $5,000 (heating and air conditioning repair or replacement is exempt under $15,000). Some Indian River County forms still show the older $2,500 threshold. Follow the current statute and your building department's instructions, and record the notice with the county clerk.

Inspections

Request inspections through the portal your building department uses. Keep the approved documents and product approvals on site, and don't cover work before it passes. The final inspection closes the permit, and your insurer may ask for proof of it later. See building inspections in Florida.

Flood zones and the beach

Indian River County's current FEMA flood maps took effect on January 26, 2023, and the county reviews permits against them. The county's flood information page explains how to look up a property, and elevation certificates for previously developed properties back to 1997 are available from the county. If your home is in a flood zone, a large remodel can trigger the FEMA 50% rule.

On the ocean side of the barrier island, the state's coastal construction control line runs from Sebastian Inlet south to the St. Lucie County line. Work seaward of it generally needs a permit from the Florida Department of Environmental Protection, with certain exceptions, as well as a building permit. See coastal construction control line permits.

Checking a contractor's license

Check every contractor at MyFloridaLicense.com. The county says a state-certified contractor must register the certificate with the county's building official before contracting in unincorporated areas or Vero Beach. "Certified" means a state license; "registered" means licensed through a local government. Indian River Shores stopped accepting county-issued certificates of competency on July 1, 2025, so ask your building department what it accepts. Our guide to checking a contractor walks through the steps.

After a hurricane

After the 2024 hurricanes, the county temporarily waived permits for certain storm repairs to one- and two-family homes, from October 14, 2024 to January 17, 2025. Waivers like that are temporary, so check your building department's current notices after a storm. Indian River Shores' post-storm plan expedites roof, window and door permits. Before signing with anyone who knocks on your door, read hurricane repair scams in Florida.

Frequently asked questions

Does the City of Vero Beach have its own building department?

No. The city shares its building department with Indian River County, so Vero Beach permits go through the county Building Division. Zoning, site plan and historic preservation approvals still come from the city's Planning and Development Department, and they are needed before the permit is issued.

How do I apply for a permit in unincorporated Indian River County?

Through the county's MyGovernmentOnline (MGO) portal, which handles applications, payments, inspection requests and document uploads. The county's scope-of-work application asks for a detailed description of the work and proof of the job value, such as a signed contract.

Do I need a permit for a fence in Indian River County?

In unincorporated areas and Vero Beach, yes. The county's fence application asks for a survey or site plan showing where the fence goes, its type and height, and any gates, and the permit needs planning sign-off. Sebastian, Fellsmere, Indian River Shores and Orchid set their own fence rules.

Can I pull my own permit as an owner-builder?

The county accepts owner-builder applications with the state's owner-builder disclosure statement, for a home you will live in and whose work you supervise yourself. Sebastian says owner-builder applications must start in person at its building department.

Does the $7,500 permit exemption apply here?

The county has a separate exemption application for limited work under $7,500 on a single-family home, following the 2026 state law. It doesn't cover electrical, plumbing, mechanical, gas or structural work, or property in a flood hazard area, and you have to apply for it.

Official sources

We summarize official information in our own words and link to the source. Requirements can change, so confirm details with the source before relying on them. Our editorial standards

Renovation Guides

Remodeling in Vero Beach and Sebastian

A local guide to remodeling in Vero Beach, Sebastian and Indian River County, with permits, wind and flood rules, septic-to-sewer and nearby St. Lucie.

Project Costs

Roof replacement cost in Vero Beach

What a new roof costs in Vero Beach, Sebastian and the Treasure Coast, published local estimates, barrier island cost drivers and local permits.

Permits & Regulations

What is a Notice of Commencement?

What a Florida Notice of Commencement is, when it's required, how to record it, and how it protects you from paying twice under the construction lien law.

Renovation Guides

How to check a contractor's license

Look up a Florida contractor on MyFloridaLicense.com, check local registration in counties like Brevard, verify workers' comp and report unlicensed work.